Work Orders / WO-2026-2040

WO-2026-2040

PM ServiceNormal priorityComplete

Engine oil change @ 250 hr interval

PM Service dispatch — field work charging to a parent Job.

↓ From:Created 2026-09-19·↑ Feeds:Labor / EQP / Materials charges via Combined Daily → Parent Job cost → Equipment maintenance history

Work Type

PM Service

Manitowoc County

Equipment

SC-114

GRDR-200

Assigned Crew

Man-Crew-1

Foreman: Casey Braun

Scheduled

9/21/26, 8:00 AM

Est 4 hrs

Parent Job

J-2026-110

CTH Y — Ditch Cleaning (SK)

Open

9/21/2026
by shop supervisor

In Progress

9/21/2026
by shop supervisor

Complete

In stage

PM Details

PM Trigger

Interval

250 hours

Last PM

7/2/2026

@ 8,200 hours

Equipment Meter

Current: 8,442 hours

Triggered @ 8,450

Service Checklist

  • Inspect at intake
  • Replace consumables per interval
  • Top off fluids
  • Test operation
  • Update PM log

Standard Parts

  • ·Engine oil4 gal
  • ·Oil filter1 ea
  • ·Air filter1 ea
  • ·Shop rags1 pkg

Charges — Labor

$220.00

6 employees, 3.7 hrs est

Charges — EQP

$90.00

1 equipment lines

Charges — Materials

$760.00

6 part lines

Total / Variance

$1,070.00 of $240.00 est

346% over budget

DateBatchEmployeeHoursOTRateCostSource
2026-09-26pbch-lab-4emp-tina-berg9—$44.00$396.00Combined Daily
2026-09-25pbch-lab-5emp-ana-rivera8—$42.00$336.00Combined Daily
2026-09-24pbch-lab-6emp-sara-mahmoud9—$38.00$342.00Combined Daily
2026-09-23pbch-lab-7emp-ren-okafor8—$32.00$256.00Combined Daily
TOTAL34 hrs$1,330.00

Estimated 4 hrs · Actual 34 hrs · Variance +30.0 hrs