Work Orders / WO-2026-1745

WO-2026-1745

RepairHigh priorityComplete

Repair — hydraulic leak at boom cylinder

Repair dispatch — field work charging to a parent Job.

↓ From:Created 2026-05-18·↑ Feeds:Labor / EQP / Materials charges via Combined Daily → Parent Job cost → Equipment maintenance history

Work Type

Repair

Sauk County

Equipment

SC-114

GRDR-200

Assigned Crew

—

Foreman: Jordan Ellis

Scheduled

—

Est 8 hrs

Parent Job

J-2026-014

STH 33 — Bituminous Patching, Sauk Segment 4

Open
In Progress
Complete

In stage

Charges — Labor

$320.00

6 employees, 5.3 hrs est

Charges — EQP

$0.00

2 equipment lines

Charges — Materials

$320.00

6 part lines

Total / Variance

$640.00 of $640.00 est

On track

DateBatchEmployeeHoursOTRateCostSource
2026-09-29bch-lab-2026-001emp-bill-hauser8—$42.84$342.72Combined Daily
2026-09-29bch-lab-2026-001emp-tina-berg8—$36.08$288.64Combined Daily
2026-09-29bch-lab-2026-001emp-doug-liu8—$35.83$286.64Combined Daily
2026-09-29bch-lab-2026-001emp-sara-mahmoud8—$36.18$369.42Combined Daily
TOTAL32 hrs$1,287.42

Estimated 8 hrs · Actual 32 hrs · Variance +24.0 hrs