Work Orders / WO-2026-2016

WO-2026-2016

PM ServiceNormal priorityComplete

Engine oil change @ 250 hr interval

PM Service dispatch — field work charging to a parent Job.

↓ From:Created 2026-09-07·↑ Feeds:Labor / EQP / Materials charges via Combined Daily → Parent Job cost → Equipment maintenance history

Work Type

PM Service

Manitowoc County

Equipment

SC-114

GRDR-200

Assigned Crew

Man-Crew-1

Foreman: Casey Braun

Scheduled

9/9/26, 8:00 AM

Est 4 hrs

Parent Job

J-2026-014

STH 33 — Bituminous Patching, Sauk Segment 4

Open

9/9/2026
by shop supervisor

In Progress

9/9/2026
by shop supervisor

Complete

In stage

PM Details

PM Trigger

Interval

250 hours

Last PM

6/20/2026

@ 8,032 hours

Equipment Meter

Current: 8,442 hours

Triggered @ 8,282

Service Checklist

  • Inspect at intake
  • Replace consumables per interval
  • Top off fluids
  • Test operation
  • Update PM log

Standard Parts

  • ·Engine oil4 gal
  • ·Oil filter1 ea
  • ·Air filter1 ea
  • ·Shop rags1 pkg

Charges — Labor

$468.00

6 employees, 7.8 hrs est

Charges — EQP

$546.00

2 equipment lines

Charges — Materials

$304.00

6 part lines

Total / Variance

$1,318.00 of $320.00 est

312% over budget

DateBatchEmployeeHoursOTRateCostSource
2026-09-29bch-lab-2026-001emp-bill-hauser8—$42.84$342.72Combined Daily
2026-09-29bch-lab-2026-001emp-tina-berg8—$36.08$288.64Combined Daily
2026-09-29bch-lab-2026-001emp-doug-liu8—$35.83$286.64Combined Daily
2026-09-29bch-lab-2026-001emp-sara-mahmoud8—$36.18$369.42Combined Daily
TOTAL32 hrs$1,287.42

Estimated 4 hrs · Actual 32 hrs · Variance +28.0 hrs