Work Orders / WO-2026-2067

WO-2026-2067

Road MaintenanceHigh priorityIn Progress

Pavement crack sealing route

Road Maintenance dispatch — field work charging to a parent Job.

↓ From:Created 2026-09-10·↑ Feeds:Labor / EQP / Materials charges via Combined Daily → Parent Job cost → Equipment maintenance history

Work Type

Road Maintenance

Sauk County

Equipment

DN-115

SPRDR-225

Assigned Crew

Sauk-Crew-2

Foreman: Bill Hauser

Scheduled

10/12/26, 8:00 AM

Est 8 hrs

Parent Job

J-2026-105

STH 10 — Cross-County Corridor (BR)

Open

9/12/2026
by shop supervisor

In Progress

9/12/2026
by shop supervisor

Complete

Charges — Labor

$841.00

6 employees, 14.0 hrs est

Charges — EQP

$327.00

1 equipment lines

Charges — Materials

$73.00

6 part lines

Total / Variance

$1,241.00 of $640.00 est

94% over budget

DateBatchEmployeeHoursOTRateCostSource
2026-09-28pbch-lab-2emp-ana-rivera9—$38.00$342.00Combined Daily
2026-09-27pbch-lab-3emp-sara-mahmoud8—$38.00$304.00Combined Daily
2026-09-26pbch-lab-4emp-ren-okafor9—$36.00$324.00Combined Daily
2026-09-25pbch-lab-5emp-mike-carlson8—$32.00$256.00Combined Daily
TOTAL34 hrs$1,226.00

Estimated 8 hrs · Actual 34 hrs · Variance +26.0 hrs