Work Orders / WO-2026-2019
WO-2026-2019
Road MaintenanceHigh priorityIn ProgressPavement crack sealing route
Road Maintenance dispatch — field work charging to a parent Job.
↓ From:Created 2026-08-17·↑ Feeds:Labor / EQP / Materials charges via Combined Daily → Parent Job cost → Equipment maintenance history
Work Type
Road Maintenance
Sauk County
Assigned Crew
Sauk-Crew-2
Foreman: Bill Hauser
Scheduled
10/6/26, 8:00 AM
Est 8 hrs
Open
8/19/2026
by shop supervisor
In Progress
8/19/2026
by shop supervisor
Complete
Charges — Labor
$537.00
6 employees, 8.9 hrs est
Charges — EQP
$639.00
1 equipment lines
Charges — Materials
$361.00
6 part lines
Total / Variance
$1,537.00 of $800.00 est
92% over budget
| Date | Batch | Employee | Hours | OT | Rate | Cost | Source |
|---|---|---|---|---|---|---|---|
| 2026-09-28 | pbch-lab-2 | emp-ana-rivera | 9 | — | $38.00 | $342.00 | Combined Daily |
| 2026-09-27 | pbch-lab-3 | emp-sara-mahmoud | 8 | — | $38.00 | $304.00 | Combined Daily |
| 2026-09-26 | pbch-lab-4 | emp-ren-okafor | 9 | — | $36.00 | $324.00 | Combined Daily |
| 2026-09-25 | pbch-lab-5 | emp-mike-carlson | 8 | — | $32.00 | $256.00 | Combined Daily |
| TOTAL | 34 hrs | $1,226.00 | |||||
Estimated 8 hrs · Actual 34 hrs · Variance +26.0 hrs
Related — DN-115
View allWO-2026-2011On Hold
Snow plow beat — STH 26
10/12/2026$953.00
WO-2026-2035On Hold
Snow plow beat — STH 26
10/8/2026$1,305.00
WO-2026-2043In Progress
Pavement crack sealing route
10/2/2026$1,289.00
WO-2026-2059On Hold
Snow plow beat — STH 26
10/4/2026$1,857.00
WO-2026-2067In Progress
Pavement crack sealing route
10/12/2026$1,241.00