WO-2026-2018

InspectionNormal priorityOpen

Annual safety inspection — operator side

Inspection dispatch — field work charging to a parent Job.

↓ From:Created 2026-08-24·↑ Feeds:Labor / EQP / Materials charges via Combined Daily → Parent Job cost → Equipment maintenance history

Work Type

Inspection

Brown County

Equipment

—

Assigned Crew

Brown-Crew-1

Foreman: Dan Horvath

Scheduled

10/5/26, 8:00 AM

Est 2 hrs

Parent Job

J-2026-018

STH 41 — Bituminous Overlay, Brown Segment 2

Open

In stage

In Progress
Complete

Charges — Labor

$514.00

6 employees, 8.6 hrs est

Charges — EQP

$608.00

6 equipment lines

Charges — Materials

$342.00

6 part lines

Total / Variance

$1,464.00 of $360.00 est

307% over budget

DateBatchEmployeeHoursOTRateCostSource
2026-09-29pbch-lab-1emp-ana-rivera8—$32.00$256.00Combined Daily
2026-09-24pbch-lab-6emp-mike-carlson9—$32.00$288.00Combined Daily
2026-09-23pbch-lab-7emp-tina-berg8—$46.00$368.00Combined Daily
2026-09-22pbch-lab-8emp-ana-rivera9—$40.00$360.00Combined Daily
TOTAL34 hrs$1,272.00

Estimated 2 hrs · Actual 34 hrs · Variance +32.0 hrs