Jobs / J-2026-018
STH 41 — Bituminous Overlay, Brown Segment 2
J-2026-018·Brown County·State·Created by Pat Keller on 2026-08-26·Scheduled: 2026-08-26 → 2026-11-29
Master record of a unit of work — every cost charged here rolls up to invoicing, year-end, and the job's parent activity codes.
↓ From:Manually created 2026-08-26 by Pat Keller·↑ Feeds:All EQP/Labor/Material lines coded to this Job (43 transactions) → Invoices (4 issued) → Equipment Cost Analysis
Effort
State
Budget
$120,000.00
Schedule
2026-08-26 → 2026-11-29
Approved By
WisDOT Region NE
Contract Ref
STH-41-2026-OVR
Period Total
$13,881.80
this fiscal period · vs prior +22%
YTD Total
$74,962.00
fiscal year 2026
$74,962.00 of $120,000.0062%
Invoiceable
$12,771.26
Last invoiced 2026-06-02 ($189,595.00)
Status
Active
Days remaining: 59 (until 2026-11-29)
| Activity | Group | Labor | EQP | Materials | Total | Budget | Variance | % Complete | Last Charged |
|---|---|---|---|---|---|---|---|---|---|
4210 — Bituminous Patching | 4200 — Surface Maintenance | $0.00 | $0.00 | $3,048.80 | $3,048.80 | $70,000.00 | +$66,951.20 | 4% | 2026-09-29 |
4220 — Concrete Patching | 4200 — Surface Maintenance | $1,586.00 | $1,230.00 | $0.00 | $2,816.00 | $28,000.00 | +$25,184.00 | 10% | 2026-09-29 |
4230 — Crack Sealing | 4200 — Surface Maintenance | $0.00 | $0.00 | $0.00 | $0.00 | $22,000.00 | +$22,000.00 | 0% | never |
| Job totals: | $1,586.00 | $1,230.00 | $3,048.80 | $5,864.80 | $120,000.00 | ||||