Work Orders / WO-2026-2045

WO-2026-2045

RepairLow priorityComplete

Alternator failure — replace

Repair dispatch — field work charging to a parent Job.

↓ From:Created 2026-08-15·↑ Feeds:Labor / EQP / Materials charges via Combined Daily → Parent Job cost → Equipment maintenance history

Work Type

Repair

Milwaukee County

Equipment

—

Assigned Crew

Mil-Shop-A

Foreman: Jordan Ellis

Scheduled

8/17/26, 8:00 AM

Est 10 hrs

Parent Job

J-2026-115

CTH A — Crack Sealing (DN)

Open

8/17/2026
by shop supervisor

In Progress

8/17/2026
by shop supervisor

Complete

In stage

Charges — Labor

$335.00

0 employees, 5.6 hrs est

Charges — EQP

$245.00

0 equipment lines

Charges — Materials

$855.00

0 part lines

Total / Variance

$1,435.00 of $600.00 est

139% over budget

DateBatchEmployeeHoursOTRateCostSource
2026-08-15B-2026-1209Casey Braun4—$60.00$167.50Combined Daily
2026-08-15B-2026-1209Bill Hauser4—$60.00$167.50Combined Daily
TOTAL8 hrs$335.00

Estimated 10 hrs · Actual 8 hrs · Variance -2.0 hrs