Work Orders / WO-2026-2039

WO-2026-2039

Road MaintenanceHigh priorityComplete

Shoulder reshape — CTH F

Road Maintenance dispatch — field work charging to a parent Job.

↓ From:Created 2026-09-26·↑ Feeds:Labor / EQP / Materials charges via Combined Daily → Parent Job cost → Equipment maintenance history

Work Type

Road Maintenance

Milwaukee County

Equipment

—

Assigned Crew

Mil-Shop-A

Foreman: Jordan Ellis

Scheduled

9/28/26, 8:00 AM

Est 8 hrs

Parent Job

J-2026-109

STH 13 — Bituminous Overlay (SK)

Open

9/28/2026
by shop supervisor

In Progress

9/28/2026
by shop supervisor

Complete

In stage

Charges — Labor

$197.00

0 employees, 3.3 hrs est

Charges — EQP

$59.00

0 equipment lines

Charges — Materials

$741.00

0 part lines

Total / Variance

$997.00 of $800.00 est

25% over budget

DateBatchEmployeeHoursOTRateCostSource
2026-09-26B-2026-1209Casey Braun4—$60.00$98.50Combined Daily
2026-09-26B-2026-1209Bill Hauser4—$60.00$98.50Combined Daily
TOTAL8 hrs$197.00

Estimated 8 hrs · Actual 8 hrs · Variance +0.0 hrs