Work Orders / WO-2026-2033

WO-2026-2033

RepairNormal priorityComplete

Brake adjustment — pulling left

Repair dispatch — field work charging to a parent Job.

↓ From:Created 2026-08-09·↑ Feeds:Labor / EQP / Materials charges via Combined Daily → Parent Job cost → Equipment maintenance history

Work Type

Repair

Milwaukee County

Equipment

—

Assigned Crew

Mil-Shop-A

Foreman: Jordan Ellis

Scheduled

8/11/26, 8:00 AM

Est 10 hrs

Parent Job

J-2026-022

STH 145 — Emergency Culvert Washout Response

Open

8/11/2026
by shop supervisor

In Progress

8/11/2026
by shop supervisor

Complete

In stage

Charges — Labor

$859.00

6 employees, 14.3 hrs est

Charges — EQP

$473.00

6 equipment lines

Charges — Materials

$627.00

6 part lines

Total / Variance

$1,959.00 of $840.00 est

133% over budget

DateBatchEmployeeHoursOTRateCostSource
2026-09-29pbch-lab-1emp-deepak-singh9—$33.00$297.00Combined Daily
2026-09-28pbch-lab-2emp-casey-braun-fmr8—$32.00$256.00Combined Daily
2026-09-23pbch-lab-7emp-doug-liu9—$35.00$315.00Combined Daily
2026-09-22pbch-lab-8emp-deepak-singh8—$48.00$384.00Combined Daily
TOTAL34 hrs$1,252.00

Estimated 10 hrs · Actual 34 hrs · Variance +24.0 hrs