Work Orders / WO-2026-2015
WO-2026-2015
Road MaintenanceHigh priorityCompleteShoulder reshape — CTH F
Road Maintenance dispatch — field work charging to a parent Job.
↓ From:Created 2026-09-14·↑ Feeds:Labor / EQP / Materials charges via Combined Daily → Parent Job cost → Equipment maintenance history
Work Type
Road Maintenance
Milwaukee County
Equipment
—
Assigned Crew
Mil-Shop-A
Foreman: Jordan Ellis
Scheduled
9/16/26, 8:00 AM
Est 8 hrs
Open
9/16/2026
by shop supervisor
In Progress
9/16/2026
by shop supervisor
Complete
In stage
Charges — Labor
$445.00
6 employees, 7.4 hrs est
Charges — EQP
$515.00
6 equipment lines
Charges — Materials
$285.00
6 part lines
Total / Variance
$1,245.00 of $480.00 est
159% over budget
| Date | Batch | Employee | Hours | OT | Rate | Cost | Source |
|---|---|---|---|---|---|---|---|
| 2026-09-29 | pbch-lab-1 | emp-bill-hauser | 9 | — | $35.00 | $315.00 | Combined Daily |
| 2026-09-28 | pbch-lab-2 | emp-dan-horvath | 8 | — | $36.00 | $288.00 | Combined Daily |
| 2026-09-27 | pbch-lab-3 | emp-doug-liu | 9 | — | $35.00 | $315.00 | Combined Daily |
| 2026-09-26 | pbch-lab-4 | emp-deepak-singh | 8 | — | $32.00 | $256.00 | Combined Daily |
| TOTAL | 34 hrs | $1,174.00 | |||||
Estimated 8 hrs · Actual 34 hrs · Variance +26.0 hrs