Work Orders / WO-2026-0871

WO-2026-0871

RepairHigh priorityIn Progress

Replace front brake pads + hydraulic line — wheel loader MIL-301

Repair dispatch — field work charging to a parent Job.

↓ From:Created 2026-09-27·↑ Feeds:Labor / EQP / Materials charges via Combined Daily → Parent Job cost → Equipment maintenance history

Work Type

Repair

Milwaukee County

Equipment

MIL-301

LOAD-300

Assigned Crew

Mil-Shop-A

Foreman: Jordan Ellis

Scheduled

9/27/26, 8:00 AM

Est 6 hrs

Parent Job

J-2026-105

STH 10 — Cross-County Corridor (BR)

Open

9/28/2026
by shop supervisor

In Progress

9/28/2026
by shop supervisor

Complete

Charges — Labor

$480.00

6 employees, 8.0 hrs est

Charges — EQP

$0.00

0 equipment lines

Charges — Materials

$642.00

6 part lines

Total / Variance

$1,122.00 of $1,150.00 est

2% under

DateBatchEmployeeHoursOTRateCostSource
2026-09-28pbch-lab-2emp-ana-rivera9—$38.00$342.00Combined Daily
2026-09-27pbch-lab-3emp-sara-mahmoud8—$38.00$304.00Combined Daily
2026-09-26pbch-lab-4emp-ren-okafor9—$36.00$324.00Combined Daily
2026-09-25pbch-lab-5emp-mike-carlson8—$32.00$256.00Combined Daily
TOTAL34 hrs$1,226.00

Estimated 6 hrs · Actual 34 hrs · Variance +28.0 hrs