Jobs / J-2026-XC-001

STH 10 — Cross-County Corridor (Brown ↔ Manitowoc)

J-2026-XC-001·Brown County·State·Created by Pat Keller on 2026-08-31·Scheduled: 2026-08-31 → 2026-12-29

Master record of a unit of work — every cost charged here rolls up to invoicing, year-end, and the job's parent activity codes.

↓ From:Manually created 2026-08-31 by Pat Keller·↑ Feeds:All EQP/Labor/Material lines coded to this Job (47 transactions) → Invoices (4 issued) → Equipment Cost Analysis

Effort

State

Budget

$95,000.00

Schedule

2026-08-31 → 2026-12-29

Approved By

WisDOT Region NE

Contract Ref

STH-10-XC-2026

Period Total

$15,952.80

this fiscal period · vs prior +22%

YTD Total

$86,145.00

fiscal year 2026

$86,145.00 of $95,000.0091%

Invoiceable

$14,676.58

Last invoiced 2026-09-15 ($31,840.00)

Status

Active

Days remaining: 89 (until 2026-12-29)

ActivityGroupLaborEQPMaterialsTotalBudgetVariance% CompleteLast Charged

4210 — Bituminous Patching

4200 — Surface Maintenance$0.00$0.00$3,460.80$3,460.80$55,000.00+$51,539.20
6%
2026-09-28

4310 — Culvert Maintenance

4300 — Drainage$0.00$0.00$0.00$0.00$25,000.00+$25,000.00
0%
never

4250 — Shoulder Repair

4200 — Surface Maintenance$2,106.00$0.00$0.00$2,106.00$15,000.00+$12,894.00
14%
2026-09-29
Job totals:$2,106.00$0.00$3,460.80$5,566.80$95,000.00